The state Public Utility Commission by a 4-1 vote this morning approved a 1-1/2-mile portion of the Trans-Allegheny Interstate Line, Allegheny Energy Inc.'s controversial high-voltage transmission line.
In a separate motion, the commission voted 3-2 to stay the remainder of the 37.2-mile portion of the 240-mile transmission line project located in the state, directing the parties to develop alternatives regarding the remainder of the project.See the full content of this document
Extract
Puc Approves Part of Controversial High-Voltage Line
Included in the approval was a planned substation -- called ...